Question
After the total slack for each activity is identified, the project manager can more easily identify the earned value critical path earliest start date total project slack total budget
Solution
4.5
(324 Votes)
Morris
Elite ยท Tutor for 8 years
Answer
# Brief Explanations:Total slack, or float, is the amount of time that an activity can be delayed without delaying the project completion date. By identifying the total slack for each activity, the project manager can determine which activities have no slack (zero slack), meaning any delay in these tasks would delay the entire project. These activities form the critical path.# Answer:critical path