A __ Must Be Completed Before the Next Task Can Begin. A. Critical Task B. Successor Task C. Predecessor Task D. Critical Path

Question

A __ must be completed before the next task can begin. a. critical task b. successor task c. predecessor task d. critical path

Solution

Expert Verified
4.5 (308 Votes)
Selah Elite ยท Tutor for 8 years

Answer

c. predecessor taskA **predecessor task** must be completed before the next task (its successor) can begin. The other options don't fit this definition:* **Critical task:** A task on the critical path, meaning it directly impacts the project's overall duration.* **Successor task:** A task that follows another.* **Critical path:** The longest sequence of tasks in a project, determining the shortest possible project duration.