Question
A __ must be completed before the next task can begin. a. critical task b. successor task c. predecessor task d. critical path
Solution
4.5
(308 Votes)
Selah
Elite ยท Tutor for 8 years
Answer
c. predecessor taskA **predecessor task** must be completed before the next task (its successor) can begin. The other options don't fit this definition:* **Critical task:** A task on the critical path, meaning it directly impacts the project's overall duration.* **Successor task:** A task that follows another.* **Critical path:** The longest sequence of tasks in a project, determining the shortest possible project duration.